Dec 2019: Phase Two Refurb complete at St. Killian’s School, Cork

We were delighted to be asked back to complete the second phase fit-out at St Killian’s School in Mayfield, Cork, having completed the much larger first phase refurb to the rest of the school building last year.

The Phase two fit-out was completed a full two weeks ahead of target.

The project was handed over to the school principal this week commencing the 9th of December.

Big effort from Site Manager Derek O’Connor, Contracts Manager Dan Casey and our subcontractor team in Cork to meet the required deadlines for our Client. Our thanks to Mary Harrington Architects for their oversight on this project.