Dec 2020: Fast Track A&E Extension at UHW Complete

Dec 2020: Fast Track A&E Extension at UHW Complete

Our third Fast Track project of the last couple of weeks, we were delighted to hand over a new Lobby Extension and Queuing Area to the A&E Department of University Hospital Waterford at 5pm on Tuesday 22nd December 2020. Works commenced on site on the 16th November 2020 and were completed in just over 5 weeks. Thank you to all of our subcontractors involved who pulled out all of the stops to help this project come together in such a short space of time. Our thanks also to the Design Team of Malone O’Regan and RKD Architects for their efforts in getting this across the line for the Christmas Break. A massive effort by all parties involved.